The Avenue R Complete Streets Project will provide for street improvements along Avenue R between Sierra Highway and 25th Street East.
This project has been awarded to Sully Miller Contracting Company and has a total project cost of more than $20 million, which will be funded through multiple sources as outlined below.
Preconstruction Work By Others | Construction Preparation | Construction Stage 1 | Construction Stage 2 | Construction Stage 3 |
---|---|---|---|---|
Nov. 2022 to Feb. 2023 | March 2023 to April 2023 | May 2023 to Nov. 2023 | Dec. 2023 to July 2024 | Aug. 2024 to Sept. 2024 |